Please click on the picture you wish to view |
|
|
|
 |
Specialist
floor contract |
|
The Concrete Company |
|
|
|
|
|
|
 |
 |
 |
|
|
|
Contractor A.B.S. Brymar Flooring
Ltd.
Site Du-bois Factory, Arkwright
Rd. Corby
Client Du-bois International
Date Dec 2000 - Jan
2001
Description Specialist floor
contract involving pours of 350 cubic metres per day, using steel
fibre reinforcement mixed into the concrete, along with a super
plasticiser. Once laid, a granite topping was powerfloated in to
provide an extra hard surface. The
Concrete Company also provided the concrete for the piling to this
site.
|
|
|

|
|
|
 |
Another job well done by The Concrete Company |
 |
|
|
 |
 |
 |
|
|
Contractor
J.A. Gammon
Site
Eissmann Way, Corby, Northants.
Client
H. C. Davis & sons Ltd.
Date
June 2001
Description
The first of four days involving 250 - 350 cubic metres of concrete
supplied from our readymix plant at Corby. The contractor
requested four truck to supply each day, starting at 5.00am on site.
The pours were usually finished well by lunchtime. This is the fourth
such contract carried out by The Concrete Company for this
client / contractor.
|
|
|

|
|
 |
Contract
by the sea
A great success |
 |
|
 |
 |
 |
|
|
Contractor
May Gurney Civil Engineering Ltd.
Site
Hunstanton Prom sea defenses.
Client Environment
Agency.
Date Jan -
March 2001.
Description
Tide times, a weight limit on the promenade itself and concrete which
required a resistance to sulphate attack were all issues for
consideration when The Concrete Company undertook this contract on the
Norfolk coastline. There was a further complication in that the work
had to be completed before the prom re opened at Easter 2001.
We dedicated our plant at Fakenham to this contract for
the duration of the daily pours. Both May Gurney and The Concrete
Company worked closely together and the contract was completed 2 weeks
early from a 2 week late start.
|
|
|

|
|
 |
 |
 |
|
 |

|
 |
|
Contractor
Stanford Flooring Ltd. Working for French Kier Ltd.
Site
New Fairline Boat facility at Oundle Northamptonshire. Description
Laser pour for the floor at the new Fairline boat production
facility. Requirement was for one cubic metre of concrete per minute
throughout the pour. Ten trucks delivering from two locations were
used.
|
|
|
|
|

|
|
|
|
Go
to Page 1 |
|
|